Skanska USA flags data centre market volatility risk
18 November 2026
The foyer of a data centre build by Skanska USA (Image: Skanska USA)
The US data centre construction market could become more volatile in 2027 amid labour constraints, inflation, and long lead times for key materials.
That’s the warning from the Fall 2026 Construction Market Trends Report, which said the commercial construction market continues to be defined by supply chain volatility, escalating power infrastructure demand, and evolving trade policy.
US domestic steel mills are nearing capacity, while recent US-Canada tariff actions and September revisions to the Section 338 tariff coverage, have increased uncertainty around the cost of some metals and other construction materials.
The new Section 38 tariffs were imposed on fabricated steel (50%), plywood (50%), and lumber (45.2%) imported from Canada and are in addition to existing Section 232 tariffs introduced by President Trump in 2025.
Fabricated steel pricing is now above 40% since the start of the year, while lead times in some markets are now over 60 weeks, the report noted.
It also highlighted the strong demand for electrical infrastructure and skilled MEP workers that is outpacing capacity amid the data centre construction boom.
Large-scale data centre generators that once required a lead time of 20-30 weeks are now commonly exceeding 100 weeks, it said.
But the conditions in local markets are still mixed, with some regions of the US experiencing the capacity constraints of data centre growth, while others are seeing less volatile inflation and good project completion levels.
But Skanska warned, “Concerns are mounting that even these more stable markets could see increased volatility in the next 18 months. With major data centre projects moving from planning to construction in 2027 and beyond, regional labour constraints could become a more widespread national challenge.”
It also noted that making early market evaluations during the planning of projects was “critical”, with projects that can secure power, labour, and long-lead materials early likely to be better positioned to maintain schedules and budgets.