Significant equipment required for HS2

05 November 2014

The UK's planned new high-speed rail line (HS2) will link London with Birmingham, Manchester, Leeds

The UK's planned new high-speed rail line (HS2) will link London with Birmingham, Manchester, Leeds and Sheffield.

At least 450 articulated dump trucks (ADTs) are forecast to be required to support peak construction of the first phase of the UK’s proposed new high-speed rail network HS2, according to John J Carroll, head of construction and logistics for the project.

Speaking at the UK Construction Plant-hire Association (CPA) Future Plant Hire Conference in October, Mr Carroll said rental companies were likely to benefit from increased demand for construction equipment as a result of the £42.6 billion (€54.2 billion) mega project linking London and the north.

The entire HS2 project envisages 563 km of track and nine stations, with multiple tunnels, bridges and viaducts.

It will be completed in two phases – the 104 km first phase will see the construction of a line from London to the West Midlands, including Birmingham, which also connects with the existing High-Speed One (HS1) network. This line is expected to open in 2026, with construction scheduled to start in 2016.

The next phase is scheduled for construction in 2022 to 2033 and extends the line in the north to Manchester and Leeds.

“For phase one of the project, at peak construction times, at least 450 ADTs will be required on site, and 600 on-highway loading trucks,” Mr Carroll said.

“If you add to that of all the excavators and other equipment needed to load these trucks, it gives you an idea of the kind of equipment demand we are expecting.”

Mr Carroll said more than 50% of the first phase of the project would involve cuttings or tunnels. In addition, around 100 bridges and viaducts are planned for this phase.

“We are forecasting 55 million m3 of excavation,” Mr Carroll said. “In addition, the first phase of the project will need around 4 million m3 concrete; 900,000 tonnes rebar; 4,500 m3 of concrete segments; 700,000 m3 of surfacing materials; and 973 km of rail line.”

In December last year, the CPA forecast that the first phase of HS2 could generate rental revenues of more than £200 million (€254 million).

STAY CONNECTED


Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

Sign up

CONNECT WITH THE TEAM
Ollie Hodges Publisher Tel: +44 (0)1892 786253 E-mail: [email protected]
Lewis Tyler
Lewis Tyler Editor Tel: 44 (0)1892 786285 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA